MerryMan Excavation
Water Main - Williston, ND Minimize

Merryman contracted with the Western Area Water Supply Authority to provide a large scale water main which needed to be built to help handle the rapid economic development in the area due to the shale oil boom.

Project Description:
30" and 24" water main  

Location:
Williston, ND

General Contractor:
Western Area Water Supply Authority

 

 

Special Features:

19,000 ft of 30" and 12,000 ft of 24" ductile water main with several blow off and air release assemblies

280 ft 42" Auger and Jack under existing highway

Notice to proceed was given August 26th and installation was completed November 18th, well in advance of completion deadline